Before It Ships: How Every Beiya Filling Machine Passes 72 Hours Of Testing

Nov 13, 2026

Leave a message

Every buyer asks the same question before signing a contract: "How do I know the machine will work when it arrives?" The honest answer is: because we already ran it. Here is what happens inside our Shenyang factory in the final week before any machine is packed for export.

Stage 1: Mechanical Verification (Day 1)

After final assembly, the machine runs empty for a full cycle: carton forming, bottom sealing, conveying, top sealing. Our engineers check:

Carton pick-up and opening success rate (target: no misfeeds in 200 consecutive cartons)

Chain and cam synchronization

Pneumatic system pressure stability

Stage 2: Water Test - 72 Hours (Days 2-4)

The machine then runs continuously for 72 hours with water:

Fill volume is sampled every hour and logged. Deviation must stay within ±1% of set volume.

No visible leakage at any rotary joint, valve, or nozzle.

Sealing integrity: each hour, sealed cartons are cut open and inspected for crease integrity and seal uniformity.

Any anomaly - even a single hour outside tolerance - sends the machine back to adjustment. The 72-hour clock restarts.

Stage 3: Product Trial (Day 5, on request)

For customers with special products - viscous cream, granule-containing drinks, powders - we run the actual product or a matched substitute before shipment and record the final parameter settings, which ship with the machine as the commissioning baseline.

Stage 4: Documentation and Packing (Day 6-7)

Every machine leaves with:

The complete 72-hour test log

Parameter baseline and lubrication chart

A spare parts package matched to the customer's first year of operation

Video-recorded commissioning reference for the customer's operators

Why We Do It This Way

A container shipment to South America or Africa takes 40-60 days. If a problem only appears at installation, the customer loses weeks waiting for engineers or parts. Running every machine for 72 hours before it enters a container is how we keep our installation success rate where it should be: above 99%.

Planning a new production line? You are welcome to witness the final test of your own machine before shipment - either in person or via live video.